Scheme Details
DISTRICT
Mau
AGENCY
GA INFRA-VPL
SCHEME ID
20091495
SCHEME NAME
CHANDRAPAR GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST
263.85
EXPENDITURE
222.22
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
18
Procured
18
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14990.00
Meter
Length Laid
13600.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Badraon | Chandrapar | 465163 | Chandrapar | 242 | 232 | 96% | Work In Progress | Not Certified |
| 2 | Mau | Badraon | Chandrapar | 465164 | Malpura | 45 | 43 | 96% | Work In Progress | Not Certified |
| 3 | Mau | Badraon | Chandrapar | 465165 | Bhatauli Udmatiya | 111 | 102 | 92% | Work In Progress | Not Certified |