Scheme Details
DISTRICT
Etawah
AGENCY
OMIL-JWIL (JV)
SCHEME ID
20091595
SCHEME NAME
BAUTH
ESTIMATED COST
422.17
EXPENDITURE
280.16
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
2
Work Started
1
Work Completed
0
Solar Plant
Required
46
Procured
46
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
21999.00
Meter
Length Laid
21000.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Jaswantnagar | Bauth | 419502 | Bauth | 797 | 725 | 91% | Work In Progress | Not Certified |