Scheme Details
DISTRICT
Etawah
AGENCY
OMIL-JWIL (JV)
SCHEME ID
20091687
SCHEME NAME
BIRARI WATER SUPPLY SCHEME
ESTIMATED COST
644.76
EXPENDITURE
266.32
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
74
Procured
74
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
25143.00
Meter
Length Laid
25000.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Bharthana | Birari | 419945 | Birari | 1575 | 1572 | 100% | Work In Progress | Not Certified |