Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Etawah | OMIL-JWIL (JV) | 20091720 | DOONGRI & KUNARA | 632.55 | 211.42 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 2 | 2 | 1 | 1 | 1 | 1 | 0 | 60 | 60 | Yes | 0 | NA | No | 27359.00 | 27025.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Etawah | Badapura | Doongari | 419657 | Saidpur Nagala Peerji | 158 | 155 | 98 | Work In Progress | Not Certified | 
| 2 | Etawah | Badapura | Kunara | 419659 | Kunara | 596 | 564 | 95 | Work In Progress | Not Certified | 
| 3 | Etawah | Badapura | Doongari | 419664 | Doongri | 186 | 181 | 97 | Work In Progress | Not Certified | 
| 4 | Etawah | Badapura | Doongari | 419666 | Harsoli | 78 | 69 | 88 | Work In Progress | Not Certified |