Scheme Details
DISTRICT
Ghazipur
AGENCY
HFCL- JWIL (JV)
SCHEME ID
20091991
SCHEME NAME
AALAMPUR W/S SCHEME (HFCL)
ESTIMATED COST
178.07
EXPENDITURE
30.15
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7598.00
Meter
Length Laid
4544.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Deokali | Aalampur | 472297 | Aalampur | 120 | 117 | 98% | Work In Progress | Not Certified |
| 2 | Ghazipur | Deokali | Aalampur | 472299 | Sahdullapur | 32 | 30 | 94% | Work In Progress | Not Certified |