Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Azamgarh M/s Sudhakara Infratech Pvt. Ltd 20092003 SARAI BHAU water supply scheme 189.50 88.24 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
4 1 1 1 1 1 0 0 16 16 Yes 0 NA No 8188.00 7177.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Azamgarh Mohammadpur Sarai Bhau 463511 Nandpur 76 72 95 Work In Progress Not Certified
2 Azamgarh Mohammadpur Sarai Bhau 463512 Sarai Bhau 60 60 100 Har Gar Jal Not Certified
3 Azamgarh Mohammadpur Sarai Bhau 463513 Makkhan Patti 41 31 76 Work In Progress Not Certified
4 Azamgarh Mohammadpur Sarai Bhau 463514 Pura Natthu 21 12 57 Work In Progress Not Certified