Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | HFCL- JWIL (JV) | 20092037 | ITAHA W/S SCHEME (HFCL) | 282.53 | 61.18 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 20 | 20 | NA | 0 | NA | No | 11331.00 | 0.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Saidpur | Itaha | 472067 | Itaha | 228 | 184 | 81 | Work In Progress | Not Certified |
| 2 | Ghazipur | Saidpur | Itaha | 472068 | Parsawa | 54 | 33 | 61 | Work In Progress | Not Certified |
| 3 | Ghazipur | Saidpur | Itaha | 472069 | Partapi Pur | 2 | 1 | 50 | Work In Progress | Not Certified |