Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | HFCL- JWIL (JV) | 20092054 | RUHEPUR W/S SCHEME (HFCL) | 288.85 | 100.77 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Mardah | Ruhepur | 472750 | Ruhi Pur | 137 | 123 | 90 | Work In Progress | Not Certified | Not Verified |
2 | Ghazipur | Mardah | Ruhepur | 472751 | Rasulpur | 47 | 42 | 89 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Mardah | Ruhepur | 472752 | Ramdoopur | 238 | 213 | 89 | Work In Progress | Not Certified | Not Verified |
4 | Ghazipur | Mardah | Ruhepur | 472753 | Mirzapur Mafi | 12 | 9 | 75 | Work In Progress | Not Certified | Not Verified |
5 | Ghazipur | Mardah | Ruhepur | 472754 | Khozapur | 27 | 25 | 93 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 20 | 20 | Yes | 0 | NA | No | 8395.00 | 7889.00 |