Scheme Details
DISTRICT
Ghazipur
AGENCY
HFCL- JWIL (JV)
SCHEME ID
20092081
SCHEME NAME
KESAW PUR W/S SCHEME (HFCL)
ESTIMATED COST
243.04
EXPENDITURE
125.85
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8042.00
Meter
Length Laid
7861.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Mohammadabad | Kesaw Pur | 473495 | Kesaw Pur | 338 | 330 | 98% | Work In Progress | Not Certified |
| 2 | Ghazipur | Mohammadabad | Kesaw Pur | 473496 | Rani Pur | 30 | 28 | 93% | Work In Progress | Not Certified |
| 3 | Ghazipur | Mohammadabad | Kesaw Pur | 473499 | Chak Alawalpur | 2 | 1 | 50% | Work In Progress | Not Certified |