Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | HFCL- JWIL (JV) | 20092082 | TARKA & AMAROPUR W/S SCHEME (HFCL) | 382.20 | 77.55 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 27 | 27 | NA | 0 | NA | No | 15772.00 | 11617.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Bhanwarkol | Amaropur | 473683 | Amaropur | 146 | 146 | 100 | Har Gar Jal | Not Certified |
| 2 | Ghazipur | Bhanwarkol | Amaropur | 473684 | Araji Budhaila | 92 | 92 | 100 | Har Gar Jal | Not Certified |
| 3 | Ghazipur | Bhanwarkol | Tarka | 473710 | Tarka | 262 | 208 | 79 | Work In Progress | Not Certified |
| 4 | Ghazipur | Bhanwarkol | Tarka | 473711 | Pindroi | 38 | 38 | 100 | Har Gar Jal | Not Certified |