Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | HFCL- JWIL (JV) | 20092095 | NUYAW & MOHAMMADPUR MANORATH W/S SCHEME (HFCL) | 238.57 | 80.18 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 0 | 1 | 0 | 0 | NA | 8 | NA | No | 12420.00 | 8428.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Kasimabad | Nuyaw | 473236 | Nuyaw | 89 | 78 | 88 | Work In Progress | Not Certified |
| 2 | Ghazipur | Kasimabad | Nuyaw | 473237 | Banderpur | 20 | 18 | 90 | Work In Progress | Not Certified |
| 3 | Ghazipur | Kasimabad | Nuyaw | 473238 | Bariyarpur Mafi | 21 | 18 | 86 | Work In Progress | Not Certified |
| 4 | Ghazipur | Kasimabad | Muhammadpur Manorath | 473239 | Mohammadpur Manorath | 139 | 128 | 92 | Work In Progress | Not Certified |
| 5 | Ghazipur | Kasimabad | Nuyaw | 473240 | Dampur | 94 | 85 | 90 | Work In Progress | Not Certified |