| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | M/s Sudhakara Infratech Pvt. Ltd | 20092100 | AKBELPUR AND KISHUNPUR AND KUTUBPUR WATER SUPPLY SCHEME | 447.40 | 173.81 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 30 | 30 | Yes | 0 | NA | No | 39073.00 | 37878.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Jahanaganj | Kishunpur | 463185 | Mahamudpur | 16 | 11 | 69 | Work In Progress | Not Certified |
| 2 | Azamgarh | Jahanaganj | Kishunpur | 463191 | Nizamudeenpur | 35 | 32 | 91 | Work In Progress | Not Certified |
| 3 | Azamgarh | Jahanaganj | Kutubpur | 463211 | Kutubpur | 155 | 150 | 97 | Har Gar Jal | Not Certified |
| 4 | Azamgarh | Jahanaganj | Akbelpur | 463226 | Akbelpur | 29 | 12 | 41 | Work In Progress | Not Certified |
| 5 | Azamgarh | Jahanaganj | Kishunpur | 463274 | Lokapur | 487 | 482 | 99 | Work In Progress | Not Certified |
| 6 | Azamgarh | Jahanaganj | Kishunpur | 680450 | Katehari | 25 | 21 | 84 | Work In Progress | Not Certified |
| 7 | Azamgarh | Jahanaganj | Kishunpur | 681391 | Kishunpur | 15 | 6 | 40 | Work In Progress | Not Certified |