Scheme Details
DISTRICT
Gorakhpur
AGENCY
NCC Ltd.
SCHEME ID
20092155
SCHEME NAME
Hundari Water Supply Scheme
ESTIMATED COST
249.42
EXPENDITURE
235.82
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16563.00
Meter
Length Laid
17256.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Uruwa | Hundari | 455793 | Hundari | 52 | 52 | 100% | Har Ghar Jal | Not Certified |
| 2 | Gorakhpur | Uruwa | Hundari | 455794 | Pipraha | 17 | 17 | 100% | Har Ghar Jal | Certified |
| 3 | Gorakhpur | Uruwa | Hundari | 455795 | Parasadi Par | 11 | 11 | 100% | Har Ghar Jal | Certified |
| 4 | Gorakhpur | Uruwa | Hundari | 455796 | Hundara | 57 | 57 | 100% | Har Ghar Jal | Certified |
| 5 | Gorakhpur | Uruwa | Hundari | 455797 | Mathiya | 38 | 38 | 100% | Har Ghar Jal | Certified |
| 6 | Gorakhpur | Uruwa | Hundari | 455798 | Bar Parwa | 79 | 79 | 100% | Har Ghar Jal | Certified |