Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Budaun | PNC-SPML-JV | 20092235 | PADAULIYA & SALARPUR WATER SUPPLY SCHEME | 435.61 | 76.02 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 15130.00 | 15130.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Salarpur | Salarpur | 401834 | Salarpur | 268 | 268 | 100 | Har Gar Jal | Not Certified |
| 2 | Budaun | Salarpur | Salarpur | 401835 | Sirsather | 113 | 113 | 100 | Har Gar Jal | Not Certified |
| 3 | Budaun | Salarpur | Padauliya | 401837 | Padauliya | 219 | 219 | 100 | Har Gar Jal | Not Certified |