Scheme Details
DISTRICT
Ayodhya
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20092293
SCHEME NAME
MARUE SAHAY SINGH WSS
ESTIMATED COST
547.55
EXPENDITURE
458.24
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
28
Procured
28
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
31231.00
Meter
Length Laid
29390.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Bikapur | MARUE SHAY SINGH | 437214 | BANSHWAN PUR | 65 | 58 | 89% | Work In Progress | Not Certified |
| 2 | Ayodhya | Bikapur | MARUE SHAY SINGH | 437215 | Marue Shay Singh | 375 | 370 | 99% | Work In Progress | Not Certified |
| 3 | Ayodhya | Bikapur | Deva Pur | 437216 | Mohmd Pur | 206 | 206 | 100% | Har Ghar Jal | Not Certified |
| 4 | Ayodhya | Bikapur | Deva Pur | 437217 | DEVA PUR | 45 | 45 | 100% | Har Ghar Jal | Not Certified |
| 5 | Ayodhya | Bikapur | MARUE SHAY SINGH | 437218 | HRIDAIPUR | 339 | 334 | 99% | Work In Progress | Not Certified |