Scheme Details
DISTRICT
Kaushambi
AGENCY
GA INFRA - BABA (JV)
SCHEME ID
20092322
SCHEME NAME
Rasoolabad Urf Koilaha GPWSS
ESTIMATED COST
327.47
EXPENDITURE
236.54
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
25
Procured
25
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13200.00
Meter
Length Laid
13200.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | Chaial | Rasoolabad Urf Koilha | 431458 | Rasoolabad Urf Koilha | 608 | 607 | 100% | Work In Progress | Not Certified |