Scheme Details
DISTRICT Kaushambi
AGENCY GA INFRA - BABA (JV)
SCHEME ID 20092413
SCHEME NAME Katari and Bhagwatpur GPWSS
ESTIMATED COST 686.24
EXPENDITURE 282.31
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 0
Procured 0 KW
Work Status NA
Electric
Required 20
Transformer Procured NA
Work Status No
Distribution Line
Total Length 27465.00 Meter
Length Laid 27465.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Kaushambi Sarsawan Bhagawatpur 431138 Bhagawatpur 312 312 100% Har Ghar Jal Not Certified
2 Kaushambi Sarsawan Katari 431141 Katari 706 706 100% Har Ghar Jal Not Certified