Scheme Details
DISTRICT
Hathras
AGENCY
BGCCPL-Ramky (JV)
SCHEME ID
20092416
SCHEME NAME
BUDHAINCH WATER SUPPLY SCHEME
ESTIMATED COST
367.15
EXPENDITURE
92.27
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
20
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10844.00
Meter
Length Laid
5000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hathras | Sehpau | Budhaich | 395839 | Budhainch | 417 | 417 | 100% | Har Ghar Jal | Not Certified |