| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | GA INFRA - BABA (JV) | 20092420 | Raipur Palra and Sengraha GOV GPWSSS | 604.31 | 248.04 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 2 | 2 | 2 | 2 | 1 | 1 | 1 | 0 | 0 | NA | 20 | NA | No | 22239.00 | 22239.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | Sarsawan | Raipur Uparhar | 431140 | Raipur Uparhar | 159 | 157 | 99 | Work In Progress | Not Certified |
| 2 | Kaushambi | Sarsawan | Sengraha | 431170 | Sengaraha | 351 | 339 | 97 | Work In Progress | Not Certified |
| 3 | Kaushambi | Sarsawan | Palra | 431171 | Palara | 351 | 347 | 99 | Work In Progress | Not Certified |
| 4 | Kaushambi | Sarsawan | Raipur Uparhar | 431180 | GHASIPUR | 190 | 185 | 97 | Work In Progress | Not Certified |