Scheme Details
DISTRICT
Amroha
AGENCY
OMIL-JWIL (JV)
SCHEME ID
20092580
SCHEME NAME
BISAWALI MUSTKAM MVS (O)
ESTIMATED COST
189.66
EXPENDITURE
81.10
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
2932.00
Meter
Length Laid
3200.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Amroha | Dhanaura | Bisawali Mustahkam | 390660 | Bisawali Mustahkam | 373 | 370 | 99% | Work In Progress | Not Certified |
| 2 | Amroha | Dhanaura | Bisawali Mustahkam | 390661 | Bisawali Ahtamali | 39 | 37 | 95% | Work In Progress | Not Certified |
| 3 | Amroha | Dhanaura | Bisawali Mustahkam | 390663 | Rampur Khadar | 67 | 65 | 97% | Work In Progress | Not Certified |
| 4 | Amroha | Dhanaura | Bisawali Mustahkam | 680054 | Meerapur Ahatmali | 40 | 39 | 98% | Work In Progress | Not Certified |