Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Larsen & Toubro Ltd | 20092590 | REHTIMALI PUR W/S SCHEME | 242.01 | 42.77 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Ghazipur | Jakhania | Rehtimali Pur | 471602 | Rehtimali Pur | 164 | 164 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Ghazipur | Jakhania | Rehtimali Pur | 471603 | Mirarehti | 135 | 134 | 99 | Work In Progress | Not Certified | Not Verified |
3 | Ghazipur | Jakhania | Rehtimali Pur | 471604 | Sanjogpur Khas | 88 | 87 | 99 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 18 | 18 | No | 0 | NA | No | 9456.00 | 9456.00 |