Scheme Details
DISTRICT
Ghazipur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20092590
SCHEME NAME
REHTIMALI PUR W/S SCHEME
ESTIMATED COST
242.01
EXPENDITURE
53.62
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
18
Procured
18
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9456.00
Meter
Length Laid
9456.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Jakhania | Rehtimali Pur | 471602 | Rehtimali Pur | 164 | 164 | 100% | Har Ghar Jal | Not Certified |
| 2 | Ghazipur | Jakhania | Rehtimali Pur | 471603 | Mirarehti | 135 | 134 | 99% | Work In Progress | Not Certified |
| 3 | Ghazipur | Jakhania | Rehtimali Pur | 471604 | Sanjogpur Khas | 88 | 87 | 99% | Work In Progress | Not Certified |