Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Larsen & Toubro Ltd | 20092668 | Basantapur Water Supply Scheme | 183.15 | 62.53 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 0 | 0 | 1 | 1 | 0 | 11 | 11 | Yes | 0 | NA | No | 8668.00 | 8668.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Reusa | Basantapur | 410898 | Basantapur | 232 | 201 | 87 | Work In Progress | Not Certified |
| 2 | Sitapur | Reusa | Basantapur | 410899 | Bhagatsikrohar | 51 | 33 | 65 | Work In Progress | Not Certified |