Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Varanasi | Larsen & Toubro Ltd | 20092760 | Kesaripur_Narur_Parmanand Pur_Bisunpur Water Supply Scheme | 652.72 | 206.06 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Varanasi | KASHI VIDYAPEETH | VISHUN PUR | 476524 | VISHUN PUR | 294 | 294 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Varanasi | KASHI VIDYAPEETH | KESHARIPUR | 476545 | KESHARIPUR | 1058 | 968 | 91 | Work In Progress | Not Certified | Not Verified |
3 | Varanasi | KASHI VIDYAPEETH | NARAUR | 476561 | VAKHANI | 137 | 137 | 100 | Har Gar Jal | Not Certified | Verified |
4 | Varanasi | KASHI VIDYAPEETH | NARAUR | 476569 | NARAUR | 224 | 219 | 98 | Work In Progress | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 49 | 49 | No | 0 | NA | No | 54029.00 | 9390.00 |