Scheme Details
DISTRICT
Bahraich
AGENCY
GA INFRA-VPL
SCHEME ID
20092783
SCHEME NAME
BELNAPARA JARWAL (VPL) PWS
ESTIMATED COST
308.85
EXPENDITURE
113.98
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9065.00
Meter
Length Laid
9000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bahraich | Jarwal | Belnapara | 442794 | Belnapara | 343 | 323 | 94% | Work In Progress | Not Certified |