Scheme Details
DISTRICT
Varanasi
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20092790
SCHEME NAME
Mirzamurad Zone 5_Gurudaspur Water Supply Scheme
ESTIMATED COST
211.36
EXPENDITURE
117.12
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
18
Procured
18
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12051.00
Meter
Length Laid
12051.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Varanasi | Arajiline | Guru Das Pur | 476456 | Guru Das Pur | 140 | 138 | 99% | Work In Progress | Not Certified |
| 2 | Varanasi | Arajiline | Guru Das Pur | 476457 | Lalapur | 104 | 99 | 95% | Work In Progress | Not Certified |
| 3 | Varanasi | Arajiline | Guru Das Pur | 476458 | Jaddupura | 128 | 126 | 98% | Work In Progress | Not Certified |