Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Bahraich
AGENCY GA INFRA-VPL
SCHEME ID 20092884
SCHEME NAME MIRZAPUR TILAK NAWABGANJ (VPL) PWS
ESTIMATED COST 334.45
EXPENDITURE 70.99
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 27
Procured 27 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 12654.00 Meter
Length Laid 12649.00 Meter

Scheme Assigned Villages

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bahraich Nawabganj Mirjapur Tilak 441739 Mirja Pur Tilak 582 416 71% Work In Progress Not Certified