Scheme Details
DISTRICT
Bahraich
AGENCY
GA INFRA-VPL
SCHEME ID
20092919
SCHEME NAME
BASANTPUR KALIKA NAWABGANJ (VPL) PWS
ESTIMATED COST
174.95
EXPENDITURE
34.42
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
5891.00
Meter
Length Laid
5800.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bahraich | Nawabganj | Basantpur Kalika | 441735 | Basantpur Kalika | 251 | 210 | 84% | Work In Progress | Not Certified |