Scheme Details
DISTRICT
Mau
AGENCY
GA INFRA-VPL
SCHEME ID
20092963
SCHEME NAME
NAWEDA GOPALPUR GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST
280.49
EXPENDITURE
217.33
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16062.00
Meter
Length Laid
16062.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Fatehpur Madraun | Newada Gopalpur | 465308 | Newada Gopalpur | 205 | 190 | 93% | Work In Progress | Not Certified |
| 2 | Mau | Fatehpur Madraun | Newada Gopalpur | 465309 | Muradarsahab | 42 | 14 | 33% | Work In Progress | Not Certified |
| 3 | Mau | Fatehpur Madraun | Newada Gopalpur | 697557 | GOPPUR | 120 | 50 | 42% | Work In Progress | Not Certified |