Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | GA INFRA - BABA (JV) | 20092964 | Gaura Jaraini Khigirpur kailai GPWSS | 725.32 | 83.25 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 0 | 0 | NA | 20 | NA | No | 27489.00 | 25989.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | Newada | Jaraini | 431544 | Jaraini | 201 | 158 | 79 | Work In Progress | Not Certified |
| 2 | Kaushambi | Newada | Jaraini | 431545 | Bhagwanpur Kotiya | 52 | 1 | 2 | Work In Progress | Not Certified |
| 3 | Kaushambi | Newada | Jaraini | 431546 | Mukundpur | 19 | 4 | 21 | Work In Progress | Not Certified |
| 4 | Kaushambi | Newada | Jaraini | 431547 | Ahladpur | 90 | 57 | 63 | Work In Progress | Not Certified |
| 5 | Kaushambi | Newada | Gaura | 431548 | Gaura | 284 | 154 | 54 | Work In Progress | Not Certified |
| 6 | Kaushambi | Newada | Gaura | 431549 | Mirzapur Chandnapur | 117 | 21 | 18 | Work In Progress | Not Certified |
| 7 | Kaushambi | Newada | Khigirpur Kailai | 431550 | Khigirpur Kailai | 642 | 575 | 90 | Work In Progress | Not Certified |