Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | GA INFRA - BABA (JV) | 20093006 | Alwara Pour kashirampur GPWSS | 642.71 | 344.49 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 0 | 0 | NA | 20 | NA | No | 22400.00 | 21700.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | Sarsawan | Pour Kashi Rampur | 431161 | Pour Kashi Rampur | 235 | 215 | 91 | Work In Progress | Not Certified |
| 2 | Kaushambi | Sarsawan | Alawara | 431163 | Alawara | 863 | 837 | 97 | Work In Progress | Not Certified |