Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gonda | Larsen & Toubro Ltd | 20093019 | Kotekhas_Bauhan Water Supply Scheme | 371.22 | 154.60 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 21 | 21 | Yes | 0 | NA | No | 39989.00 | 0.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gonda | Chhapia | Bauhan | 446270 | Bichhiadar | 134 | 130 | 97 | Work In Progress | Not Certified |
| 2 | Gonda | Chhapia | Bauhan | 446271 | Bauhan | 132 | 132 | 100 | Har Gar Jal | Not Certified |
| 3 | Gonda | Chhapia | Bauhan | 446272 | Gaura Buzurg | 76 | 71 | 93 | Work In Progress | Not Certified |
| 4 | Gonda | Chhapia | Bauhan | 446273 | Bhagvanpur | 48 | 43 | 90 | Work In Progress | Not Certified |
| 5 | Gonda | Chhapia | Kote Khas | 446276 | Banganva | 39 | 39 | 100 | Har Gar Jal | Not Certified |
| 6 | Gonda | Chhapia | Kote Khas | 446277 | Kote Khas | 215 | 213 | 99 | Work In Progress | Not Certified |