Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Vindhya-GAJA (JV) | 20093067 | GHAGHOPUR Water Supply Scheme | 393.21 | 257.70 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 21260.00 | 23980.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Katehari | Ghaghopur | 438893 | Ghaghopur | 235 | 232 | 99 | Work In Progress | Not Certified | 
| 2 | Ambedkar Nagar | Katehari | Domnepur | 438895 | Domnepur | 116 | 113 | 97 | Work In Progress | Not Certified | 
| 3 | Ambedkar Nagar | Katehari | Domnepur | 438896 | Dullapur | 104 | 101 | 97 | Work In Progress | Not Certified | 
| 4 | Ambedkar Nagar | Katehari | Domnepur | 438897 | Khitabpur | 21 | 19 | 90 | Work In Progress | Not Certified |