Scheme Details
DISTRICT Bahraich
AGENCY GA INFRA-VPL
SCHEME ID 20093179
SCHEME NAME PIPARI MAFI SHIVPUR (VPL) PWS
ESTIMATED COST 332.60
EXPENDITURE 125.02
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 10203.00 Meter
Length Laid 10181.00 Meter

Scheme Assigned Villages

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bahraich Shivpur Pipri Mafi 441943 Pipri Mafi 766 762 99% Work In Progress Not Certified