Scheme Details
DISTRICT
Prayagraj
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20093212
SCHEME NAME
PANNUPUR_KORARI WATER SUPPLY SCHEME
ESTIMATED COST
350.40
EXPENDITURE
154.60
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
25442.00
Meter
Length Laid
25400.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | SRINGVERPUR DHAM | KORARI | 431685 | KORARI | 337 | 321 | 95% | Work In Progress | Not Certified |
| 2 | Prayagraj | SRINGVERPUR DHAM | PANNUPUR | 431689 | PANNUPUR | 292 | 259 | 89% | Work In Progress | Not Certified |