Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Larsen & Toubro Ltd | 20093309 | NAGAWA W/S SCHEME | 251.69 | 83.48 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | NA | 10 | NA | No | 14846.39 | 11720.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Kasimabad | Nagawa | 473157 | Nagawa | 205 | 205 | 100 | Har Gar Jal | Not Certified |
| 2 | Ghazipur | Kasimabad | Nagawa | 473158 | Ahiyapur | 2 | 1 | 50 | Work In Progress | Not Certified |
| 3 | Ghazipur | Kasimabad | Nagawa | 473159 | Chak Baksan | 30 | 30 | 100 | Har Gar Jal | Not Certified |
| 4 | Ghazipur | Kasimabad | Nagawa | 473160 | Paraji Pah | 148 | 145 | 98 | Work In Progress | Not Certified |
| 5 | Ghazipur | Kasimabad | Nagawa | 473161 | Sadhapur | 126 | 107 | 85 | Work In Progress | Not Certified |