Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Vindhya-GAJA (JV) | 20093314 | BAHERAWA Water Supply Scheme | 380.42 | 161.08 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 2 | 2 | 2 | 2 | 2 | 1 | 1 | 29 | 29 | Yes | 0 | NA | No | 12201.00 | 12100.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Unchahar | Baherawa | 417638 | Baherawa | 347 | 332 | 96 | Work In Progress | Not Certified |
| 2 | Raebareli | Unchahar | Baherawa | 417639 | Dhamdhama | 147 | 114 | 78 | Work In Progress | Not Certified |