Scheme Details
DISTRICT
Raebareli
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20093352
SCHEME NAME
PINDARI KHURD Water Supply Scheme
ESTIMATED COST
336.32
EXPENDITURE
195.04
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
2
Work Started
1
Work Completed
1
Solar Plant
Required
26
Procured
26
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7824.00
Meter
Length Laid
6983.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Raebareli | Amawan | Pindari Khurd | 416739 | Pindari Khurd | 313 | 278 | 89% | Work In Progress | Not Certified |