Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Gonda | Larsen & Toubro Ltd | 20093461 | Mandaf_Pikaura Buzurg Water Supply Scheme | 228.76 | 83.10 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 14 | 14 | Yes | 0 | NA | No | 13966.00 | 13966.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gonda | Chhapia | MANDAP | 446223 | PIPRA BUZURG | 32 | 3 | 9 | Work In Progress | Not Certified | 
| 2 | Gonda | Chhapia | Pikaura Buzurg | 446224 | Pikaura Buzurg | 153 | 3 | 2 | Work In Progress | Not Certified | 
| 3 | Gonda | Chhapia | Pikaura Buzurg | 446225 | Mahtinian | 63 | 3 | 5 | Work In Progress | Not Certified | 
| 4 | Gonda | Chhapia | MANDAP | 446226 | DHANDH BUZURG | 78 | 3 | 4 | Work In Progress | Not Certified | 
| 5 | Gonda | Chhapia | MANDAP | 446227 | BHELAKHA | 126 | 3 | 2 | Work In Progress | Not Certified | 
| 6 | Gonda | Chhapia | MANDAP | 638040 | mandap | 178 | 3 | 2 | Work In Progress | Not Certified |