Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Mau | GA INFRA-VPL | 20093559 | BANDHANPUR GRAM PANCHAYAT WATER SUPPLY SCHEME | 219.11 | 163.22 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 16 | 17 | Yes | 0 | NA | No | 13671.00 | 12985.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Dohri Ghat | BANDHAN PUR | 464933 | Ghur Pur | 1 | 1 | 100 | Har Gar Jal | Certified | 
| 2 | Mau | Dohri Ghat | BANDHAN PUR | 464934 | Chakhasan Pur Chakayat | 98 | 98 | 100 | Har Gar Jal | Certified | 
| 3 | Mau | Dohri Ghat | BANDHAN PUR | 464935 | Mubarak Pur | 2 | 2 | 100 | Har Gar Jal | Certified | 
| 4 | Mau | Dohri Ghat | BANDHAN PUR | 703500 | BANDHAN PUR | 74 | 74 | 100 | Har Gar Jal | Certified |