Scheme Details
DISTRICT
Baghpat
AGENCY
LC INFRA
SCHEME ID
20093598
SCHEME NAME
Tigri W/S SCHEME
ESTIMATED COST
117.86
EXPENDITURE
55.62
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
11
Procured
11
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
2567.00
Meter
Length Laid
2500.00
Meter
Scheme Assigned Villages
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Baghpat | Khekara | Dagarpur | 392171 | Tigri | 163 | 147 | 90% | Work In Progress | Not Certified |