Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | JAKSON - VISHVARAJ (JV) | 20093610 | BATAULI GP wss | 211.19 | 107.27 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 13 | 13 | Yes | 0 | NA | No | 15467.00 | 13500.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Vikramjot | Batauli | 450094 | Batauli | 129 | 106 | 82 | Work In Progress | Not Certified |
| 2 | Basti | Vikramjot | Batauli | 450095 | Baidauliya | 23 | 20 | 87 | Work In Progress | Not Certified |
| 3 | Basti | Vikramjot | Batauli | 450096 | Kashipur | 3 | 2 | 67 | Work In Progress | Not Certified |
| 4 | Basti | Vikramjot | Batauli | 450097 | Sarverpur | 39 | 27 | 69 | Work In Progress | Not Certified |
| 5 | Basti | Vikramjot | Batauli | 450098 | Pahi Mafi | 38 | 31 | 82 | Work In Progress | Not Certified |
| 6 | Basti | Vikramjot | Batauli | 450099 | Pure Laxmi Ram | 4 | 1 | 25 | Work In Progress | Not Certified |