Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Rithwik-Koya (JV) | 20093669 | BARDIHA JJM | 216.65 | 79.13 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 10370.00 | 11390.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Barhalganj | Bardiha | 457459 | Bardiha | 150 | 150 | 100 | Har Gar Jal | Not Certified |
| 2 | Gorakhpur | Barhalganj | Bardiha | 457460 | Ajayapura | 35 | 35 | 100 | Har Gar Jal | Not Certified |
| 3 | Gorakhpur | Barhalganj | Bardiha | 457461 | Khairati | 40 | 39 | 98 | Work In Progress | Not Certified |
| 4 | Gorakhpur | Barhalganj | Bardiha | 457462 | Gorakhpura | 17 | 8 | 47 | Work In Progress | Not Certified |