Scheme Details
DISTRICT
Gorakhpur
AGENCY
Rithwik-Koya (JV)
SCHEME ID
20093684
SCHEME NAME
JOTMAMAPAR JJM
ESTIMATED COST
196.03
EXPENDITURE
36.37
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
0
Air Compressor Done
0
O.P. Unit Done
0
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6350.00
Meter
Length Laid
6035.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Gorakhpur | Piprauli | Jotmamapar | 455206 | Jot Suklahi | 96 | 95 | 99% | Work In Progress | Not Certified |
| 2 | Gorakhpur | Piprauli | Jotmamapar | 455207 | Jotmamapar | 78 | 77 | 99% | Work In Progress | Not Certified |
| 3 | Gorakhpur | Piprauli | Jotmamapar | 455208 | Shivghat | 14 | 4 | 29% | Work In Progress | Not Certified |
| 4 | Gorakhpur | Piprauli | Jotmamapar | 455209 | Jot Darwa | 87 | 76 | 87% | Work In Progress | Not Certified |
| 5 | Gorakhpur | Piprauli | Jotmamapar | 455214 | Jot Sojawar | 13 | 6 | 46% | Work In Progress | Not Certified |