Scheme Details
DISTRICT
Auraiya
AGENCY
GVPR
SCHEME ID
20093720
SCHEME NAME
Airwakuli PWS
ESTIMATED COST
600.59
EXPENDITURE
406.86
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
46
Procured
46
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16190.00
Meter
Length Laid
16190.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Airwakatra | Airwa Kuili | 420187 | Bhatpura | 424 | 403 | 95% | Work In Progress | Not Certified |
| 2 | Auraiya | Airwakatra | Airwa Kuili | 420188 | Airwa Kuili | 592 | 580 | 98% | Work In Progress | Not Certified |