Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | NCC Ltd. | 20093780 | AZIZPUR TA NAUGAWAN & KOHNI GP MULTI VILLAGE WSS | 268.45 | 168.36 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 14 | 14 | Yes | 0 | NA | No | 17174.00 | 17174.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | Dadrol | AZIZPUR TA NAUGAVAN | 407160 | SHIVRA ELAQA GOVARSADA | 208 | 208 | 100 | Har Gar Jal | Not Certified |
| 2 | Shahjahanpur | Dadrol | Kohni | 407167 | Kohni | 145 | 145 | 100 | Har Gar Jal | Not Certified |
| 3 | Shahjahanpur | Dadrol | Kohni | 407168 | Khiria Arazi Pingri | 25 | 25 | 100 | Har Gar Jal | Not Certified |
| 4 | Shahjahanpur | Dadrol | AZIZPUR TA NAUGAVAN | 681476 | Azizpur T. Sunaura Azmatpur | 152 | 152 | 100 | Har Gar Jal | Not Certified |