Scheme Details
DISTRICT
Maharajganj
AGENCY
Rithwik-Koya (JV)
SCHEME ID
20093799
SCHEME NAME
PRASH KHAR VILLAGE WSS
ESTIMATED COST
158.46
EXPENDITURE
73.71
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
6144.00
Meter
Length Laid
7538.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Maharajganj | Pharenda | Parash Khar | 454137 | Parash Khar | 196 | 196 | 100% | Har Ghar Jal | Not Certified |