Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Budaun PNC-SPML-JV 20094180 KUDHAULI WATER SUPPLY SCHEME 260.86 70.12 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
2 1 1 1 1 1 1 0 20 20 NA 0 NA No 7081.00 7081.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Budaun Bisauli Kudhauli 401353 Kudhauli 189 188 99 Work In Progress Not Certified
2 Budaun Bisauli Kudhauli 401354 Nizara 149 148 99 Work In Progress Not Certified