Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | HFCL- JWIL (JV) | 20094413 | BHURKURA & GAJADHAR PUR W/S SCHEME (HFCL) | 427.54 | 151.01 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 13 | 13 | NA | 0 | NA | No | 17760.00 | 12284.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Jakhania | Gajadhar Pur | 471475 | Gajadhar Pur | 88 | 79 | 90 | Work In Progress | Not Certified |
| 2 | Ghazipur | Jakhania | Gajadhar Pur | 471476 | Birbhanpur | 25 | 19 | 76 | Work In Progress | Not Certified |
| 3 | Ghazipur | Jakhania | Gajadhar Pur | 471477 | Gorhara | 129 | 85 | 66 | Work In Progress | Not Certified |
| 4 | Ghazipur | Jakhania | Bhurkura | 471564 | Bhurkura | 677 | 645 | 95 | Work In Progress | Not Certified |