Scheme Details
DISTRICT
Siddharth Nagar
AGENCY
JAKSON - VISHVARAJ (JV)
SCHEME ID
20094423
SCHEME NAME
MISHTOLIYA AND TELIYA DIH GP WSS
ESTIMATED COST
393.57
EXPENDITURE
145.09
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16203.00
Meter
Length Laid
16200.00
Meter
Scheme Assigned Villages
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Siddharth Nagar | Domariyaganj | Mishroliya | 448519 | Mishraulia | 141 | 141 | 100% | Har Ghar Jal | Not Certified |
| 2 | Siddharth Nagar | Domariyaganj | Mishroliya | 448520 | Dokara | 54 | 54 | 100% | Har Ghar Jal | Not Certified |
| 3 | Siddharth Nagar | Domariyaganj | Teliya Dih | 448522 | Taliya Deha | 184 | 182 | 99% | Work In Progress | Not Certified |
| 4 | Siddharth Nagar | Domariyaganj | Teliya Dih | 448523 | Chetra | 97 | 96 | 99% | Work In Progress | Not Certified |