Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Mau | KLSR - RAYS (JV) | 20094444 | AKBARPUR GRAM PANCHAYAT WATER SUPPLY SCHEME | 252.97 | 100.70 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 20 | 20 | No | 0 | NA | No | 15517.00 | 13564.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Ranipur | Akbar Pur | 466151 | Akbar Pur | 262 | 259 | 99 | Work In Progress | Not Certified |
| 2 | Mau | Ranipur | Akbar Pur | 466152 | Khalilpur | 59 | 51 | 86 | Work In Progress | Not Certified |
| 3 | Mau | Ranipur | Akbar Pur | 466153 | Tandwa | 53 | 51 | 96 | Work In Progress | Not Certified |
| 4 | Mau | Ranipur | Akbar Pur | 681240 | Haibatpur | 4 | 1 | 25 | Work In Progress | Not Certified |